Construction of a simple 30 x 30 foot concrete slap to provide a firm, level surface that will safely support helicopter landings and loading of injured persons needing air ambulance transport.
Location
Within an existing wildlife opening approximately 150 yards north of AR State Highway 14
Project timeline
1
Scoping Start
06/06/2016
2
Comment Period
04/05/2017
3
Decision
05/2017 (Estimated)
4
Implementation
07/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| Hotard Helispot Improvement Project | Decision Signed Date: 05/31/2017 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Sylamore Ranger District |
| Legal Land Description | T15N-R11W Sec. 8 |