Removal of down and damaged timber covering approximately 191 acres on the Wedington Unit. Damage caused by several wind events in March, April, and May 2019.
Location
Lake Wedington Area : sections 3 and 4 in T 16N R 32W in Washington County. Chambers Springs Area: section 13 in T 17N R 33W; sections 18 and 19 of T 17N R 32W Benton County
Project timeline
1
Scoping Start
05/20/2019
2
Decision
06/2019 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Wedington Salvage Project | Decision Signed Date: 06/24/2019 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Boston Mountain Ranger District |
| Legal Land Description | Not Applicable |