This project would replace a undersized culvert on Copper Springs Road(site 2), replace a low water crossing with a large culvert on lower brock (site 1), and stabilize scouring downstream of a concrete box culvert on Campbell hollow county road 3.
Location
The project is located in the southeast corner of the district approximately 3 miles north of the community of Jerusalem.
Project timeline
1
Scoping Start
03/04/2019
2
Comment Period
05/21/2019
3
Decision
06/2019 (Estimated)
4
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Watershed Improvements |
| 2019 CFLRP Fish Passage | Decision Signed Date: 06/11/2019 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Bayou Ranger District |
| Legal Land Description | T9N-R17W Sec. 2&8, T10N-R17W Sec. 18 |