Replace existing utility lines crossing North Sylamore Creek
Location
Blanchard Springs recreation area complex
Project timeline
1
Scoping Start
04/24/2020
2
Decision
05/2023 (Estimated)
3
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Blanchard Springs Recreation Area Complex Electric Utility Replacement | Decision Signed Date: 04/19/2021 |
| Blanchard Springs Recreation Area Complex Utility Replacement Project | Decision Signed Date: 05/23/2023 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Sylamore Ranger District |
| Legal Land Description | Not Applicable |