Repair of bridge on Shores Lake Road including both the bridge structure itself and rehabilitation of the channel up and downstream.
Location
One mile east of Shores Lake.
Project timeline
1
Scoping Start
05/05/2021
2
Decision
05/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Travel Management; Watershed Improvements |
| Spirits Creek Bridge Repair Project | Decision Signed Date: 05/25/2021 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Boston Mountain Ranger District |
| Legal Land Description | Not Applicable |