Convert water system at the Wedington Recreational Area from the current well water system to the Washington County public water system. Requires the construction of a new waterline along an existing road to tie into municipal line.
Location
South of Lake Wedington to proclamation boundary along road 95630B.
Project timeline
1
Scoping Start
11/09/2021
2
Decision
06/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Wedington Waterline Project | Decision Signed Date: 06/01/2023 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Boston Mountain Ranger District |
| Legal Land Description | sections 9 and 10 in T 16N R 32W |