Utility Company request amend their existing permit to include a new buried electrical utility corridor (1,515 ft long x 30 ft wide--approximately 1.1 acre) & to add a second service line in an existing underground electrical corridor.
Location
Blanchard Springs Developed Recreation Area
Project timeline
1
Scoping Start
03/27/2025
2
Decision
05/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Use Permit SYL0023 Amendment 4 | Decision Signed Date: 05/14/2025 |
| Forests | Ozark-St. Francis National Forests |
| Districts | Sylamore Ranger District |
| Legal Land Description | Not Applicable |