Decision Memo Completed

Tennessee Gas Pipeline Permit Reauthorization

National Forests and Grasslands in Texas San Jacinto, Texas Sam Houston Ranger District

Reauthorization of expired pipeline permit.

Location

Pipeline runs through Compartments 94, 95, 101, 103, 104, 105, 107, 111, 112, & 113

Project timeline

1
Scoping Start
07/02/2009
2
Decision
01/2010 (Estimated)
3
Implementation
04/2010 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Renewal of the Pipeline Right-of-Way Special Use PermitDecision Signed Date: 01/21/2010
ForestsNational Forests In Texas
DistrictsSam Houston Ranger District
Minerals and geology