Project is an exploratory three-dimensional seismic survey (Shelby South Phase 1) on the north end of the Sabine National Forest. Covers approximately 80 sq miles (51,182 acres) in compartments 8-30, 32, 34-50, 54-59, 61-64, and 65.
Location
80 square miles (51,182 acres) in compartments 8-30, 32, 34-50, 54-59, 61-64, and 65 on the Sabine National Forest
Project timeline
1
Scoping Start
01/05/2010
2
Decision
08/2010 (Estimated)
3
Implementation
09/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Geokinetics, Inc. (formally known as PGS Onshore)Shelby South Phase 1 3D | Decision Signed Date: 08/25/2010 |
| Forests | National Forests In Texas |
| Districts | Sabine Ranger District |