Eastex Telephone Co is proposing to install via horizonal directional drilling 42,800 ft of fiber optics cable within the cleared right of way of FM 2694 & FM 3471, Sabine N.F.
Location
Sabine National Forest, Compartments 15, 16, 18, & 19.
Project timeline
1
Scoping Start
02/03/2011
2
Decision
09/2011 (Estimated)
3
Implementation
10/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Eastex Telephone Cooperative, Inc.Fiber Optics Cable Special Use Permit | Decision Signed Date: 09/26/2011 |
| Forests | National Forests In Texas |
| Districts | Sabine Ranger District |