Decision Memo Completed

ShoCo Production LP BCF#2 - Gas Pipeline Right-of-Way Special Use Permit

National Forests and Grasslands in Texas Sabine, Texas Sabine Ranger District

gas pipeline for the Bourghs Creek Federal #2 well.

Location

Aministrative compartment 69

Project timeline

1
Scoping Start
11/19/2010
2
Decision
05/2011 (Estimated)
3
Implementation
06/2011 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Shoco Production L.P.Gas Pipeline Right-of-Way Special Use PermitDecision Signed Date: 05/04/2011
ForestsNational Forests In Texas
DistrictsSabine Ranger District
Legal Land DescriptionTract S-1Ap-I
Minerals and geologySpecial use management