New above ground powerline to provide electricity to a private tract of land surrounded by National Forest System land
Location
The power line will be located south of the Oak Grove Church in Administrative Compartment 35 about 13 miles southeast of Broaddus TX
Project timeline
1
Scoping Start
12/16/2010
2
Decision
02/2011 (Estimated)
3
Implementation
05/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Deep East Texas Electric Coop Special Use Permit Amendment Strickland Power | Decision Signed Date: 02/15/2011 |
| Forests | National Forests In Texas |
| Districts | Angelina Ranger District |
| Legal Land Description | Tract A-2v-II |