Deep East Texas Electric Cooperative has 6 powerline special use permits that have expired and need to be renewed. The project involves only administrative changes. No new facilities or increase in scope or intensity of activities are authorized.
Location
Powerlines are located in various locations on the Angelina National Forest
Project timeline
1
Scoping Start
03/22/2011
2
Decision
11/2011 (Estimated)
3
Implementation
12/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Deep East Texas Electric Cooperative, Inc.Powerline ROW Special Use Permit | Decision Signed Date: 11/29/2011 |
| Forests | National Forests In Texas |
| Districts | Angelina Ranger District |