12 inch gas pipeline right-of-way adjacent to FM 2694 on the Sabine NF
Location
Compartment 9,15,16 & 19 on the Sabine NF. Along FM2694
Project timeline
1
Scoping Start
09/30/2011
2
Comment Period
12/16/2012
3
Decision
09/2013 (Estimated)
4
Implementation
12/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| TPF II East Texas gathering, LLC Newfield Huxley Gas Pipeline SUP | Decision Signed Date: 09/16/2013 Legal Notice Date: 09/18/2013 |
| Forests | National Forests In Texas |
| Districts | Sabine Ranger District |
| Legal Land Description | Tracts S-1a-I and S-1a-II |