Environmental Assessment Completed

TPF II East texas gathering, LLC - Newfield-Huxley Gas Pipeline Special use Permit

National Forests and Grasslands in Texas Shelby, Texas Sabine Ranger District

12 inch gas pipeline right-of-way adjacent to FM 2694 on the Sabine NF

Location

Compartment 9,15,16 & 19 on the Sabine NF. Along FM2694

Project timeline

1
Scoping Start
09/30/2011
2
Comment Period
12/16/2012
3
Decision
09/2013 (Estimated)
4
Implementation
12/2013 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
TPF II East Texas gathering, LLC Newfield Huxley Gas Pipeline SUPDecision Signed Date: 09/16/2013 Legal Notice Date: 09/18/2013
ForestsNational Forests In Texas
DistrictsSabine Ranger District
Legal Land DescriptionTracts S-1a-I and S-1a-II
Minerals and geologySpecial use management