Proposal to upgrade existing underground communications line along FM 1280, State Highway 94, & US Highway 287, in Compartments 86, 89, 92, 96, and 97.
Location
Compartments 86, 89, 92, 96, and 97
Project timeline
1
Scoping Start
10/05/2011
2
Decision
11/2011 (Estimated)
3
Implementation
12/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Use Permit Windstream Comm. Inc. Upgrade to Fiber Optic Lines | Decision Signed Date: 11/09/2011 |
| Forests | National Forests In Texas |
| Districts | Davy Crockett Ranger District |
| Legal Land Description | C-86 & 89 are 1 & 5 miles northwest of Groveton, C-96 &98 are 1-3 miles southeast of Groveton. C-92 is 4 miles north of Groveton. |