Issuance of speical use permits for existing powerline right-of-ways to replace expired speical use permits on the Angelina NF.
Location
Angelina & Jasper county
Project timeline
1
Scoping Start
05/10/2012
2
Comment Period
06/01/2012
3
Decision
07/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Jasper-Newton Electric Cooperative, Inc. Powerline SUP Reissuance Project | Decision Signed Date: 07/12/2012 Legal Notice Date: 07/17/2012 |
| Forests | National Forests In Texas |
| Districts | Angelina Ranger District |