Decision Memo Completed

Burrantown Repeater Tower Power Line SUP

National Forests and Grasslands in Texas Houston, Texas Davy Crockett Ranger District

Proposal to widen rights-of-way along National Forest System Roads 526 and 526T to allow construction of a power line, providing electricity to a new communication tower.

Location

Compartment 9

Project timeline

1
Scoping Start
08/22/2012
2
Comment Period
08/22/2012
3
Decision
12/2012 (Estimated)
4
Implementation
01/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityLand Use Adjustments
526 Spur Repeater Tower Power Line SUPDecision Signed Date: 12/04/2012 Legal Notice Date: 12/06/2012
ForestsNational Forests In Texas
DistrictsDavy Crockett Ranger District
Legal Land DescriptionCompt. 9 is located about 8 miles northwest of Ratcliff, Texas.
Special use management