Mid-South Synergy proposes to add approximately 3,200 feet of overhead powerline within the FM 149 ROW.
Location
Compartments 6 & 7
Project timeline
1
Scoping Start
09/27/2012
2
Comment Period
09/27/2012
3
Decision
02/2013 (Estimated)
4
Implementation
05/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Mid-South Synergy Phase 1 Special Use Permit | Decision Signed Date: 02/11/2013 |
| Forests | National Forests In Texas |
| Districts | Sam Houston Ranger District |
| Legal Land Description | Compartments 6 & 7 is located approximately 5 miles east of Richards, TX |