Eagel Rock aquired existing gas pipelines from Anadarko and MTI. The Forest Service needs to close the Anadarko and MTI permits and issue a permit to Eagle Rock for these existing uses.
Location
administrative compartments 127, 129, 132, 134, 135
Project timeline
1
Scoping Start
02/06/2013
2
Comment Period
03/12/2013
3
Decision
04/2013 (Estimated)
4
Implementation
06/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Eagle Rock Pipeline Right-of-Way Special Use Permit | Decision Signed Date: 04/24/2013 Legal Notice Date: 04/29/2013 |
| Forests | National Forests In Texas |
| Districts | Sabine Ranger District |
| Legal Land Description | Tracts S-20, S-2Ac, S20e, and S-2Ad-I |