Mid-South Synergy has made a proposal to convert an already existing overhead powerline to an underground line.
Location
Compartments 14, 15, 31 & 33 - Line parallels FM 149 to the west to the FM 149 S. LSHT Trailhead where it heads east to the Hidden Forest Subdivision.
Project timeline
1
Scoping Start
06/12/2013
2
Comment Period
07/03/2013
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Mid-South Synergy Phase 3 Special Use Permit Amendment | Decision Signed Date: 08/29/2013 Legal Notice Date: 09/05/2013 |
| Forests | National Forests In Texas |
| Districts | Sam Houston Ranger District |
| Legal Land Description | Not Applicable |