Decision Memo Completed

Mid-South Synergy SUP Amendment: FM 1791

National Forests and Grasslands in Texas Montgomery; Walker, Texas Sam Houston Ranger District

To add approximately 19,750 feet of new overhead & underground powerline in the FM 1791 ROW. The new line will backfeed electricity to existing lines if/when lines go down as the result of accident or natural disaster.

Location

Western ditchline of the FM 1791 ROW.

Project timeline

1
Scoping Start
04/28/2014
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Mid-South Synergy SUP Amendment: FM 1791Decision Signed Date: 07/28/2014
ForestsNational Forests In Texas
DistrictsSam Houston Ranger District
Legal Land DescriptionNot Applicable
Special use management