reissue a Special Use Permit for a new term. Permit will authorize the use and maintenance of existing 25 foot pipeline ROW that crosses approximately 4.85 miles of the SHNF.
Location
Compartments: 60, 61, 62, 64, 65, 67 & 68
Project timeline
1
Scoping Start
07/01/2014
2
Decision
09/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Explorer Pipeline Special Use Permit Reissuance | Decision Signed Date: 09/30/2014 Legal Notice Date: 09/30/2014 |
| Forests | National Forests In Texas |
| Districts | Sam Houston Ranger District |
| Legal Land Description | Not Applicable |