The Sabine River Authority as part of their obligations under their recently re-issued Federal Energy Regulatory Commission (FERC) license, is proposing to implement a plan involving improvements to 4 recreation areas on the Sabine NF.
Location
Administrative Compartments 38, 102, 110, and 138.
Project timeline
1
Scoping Start
10/30/2015
2
Decision
06/2016 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| SRA Recreation Area Capital Improvements and Maintenance Project | Decision Signed Date: 06/13/2016 |
| Forests | National Forests In Texas |
| Districts | Sabine Ranger District |
| Legal Land Description | Not Applicable |