Transfer use of existing authorization from one operator to another; reconstruction of exiting FS structure to accommodate an additional power line. No change to right of way length or width..
Location
2.5 miles east of Huntsville, TX (Compartment 58), 6 miles southeast of Huntsville, TX (Compartment 65), and 3 miles northeast of New Waverly, TX (Compartment 68).
Project timeline
1
Scoping Start
11/29/2018
2
Decision
05/2019 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Entergy Texas, Inc. SUP Amendment: Compartment 58, 65, and 68 | Decision Signed Date: 05/20/2019 |
| Forests | National Forests In Texas |
| Districts | Sam Houston Ranger District |
| Legal Land Description | Not Applicable |