Decision Memo Completed

Hilcorp Energy Company SUP Issuance: Compartment 119

National Forests and Grasslands in Texas San Augustine, Texas National Forests In Texas All Units

Installation of 2,300 feet of new pipeline through an existing right-of-way by Hilcorp Energy Company to connect Well (Foster D.1) to an existing gas gathering pipeline.

Location

5.6 miles north west of Cleveland, Texas (Compartment 119). The existing right-of-way runs adjacent to NFSR 274E.

Project timeline

1
Scoping Start
12/18/2018
2
Decision
08/2019 (Estimated)
3
Implementation
08/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Hilcorp Energy Company Special Use Permit Issuance: Compartment 119Decision Signed Date: 08/22/2019
ForestsNational Forests In Texas
DistrictsSam Houston Ranger District
Legal Land DescriptionNot Applicable
Special use management