Decision Memo Completed

Oncor Electric Delivery Company Powerline Special Use Permit Amendment

National Forests and Grasslands in Texas Angelina, Texas Angelina Ranger District

installation, operation, and maintenance of an overhead powerline right-of-way (ROW) which would connect two existing powerlines. Connection of these two existing powerlines will provide the ability to switch between the two sources of power.

Location

administrative Compartment 53, east side of FM 2109

Project timeline

1
Scoping Start
04/08/2021
2
Decision
12/2021 (Estimated)
3
Implementation
01/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Oncor Electric Delivery Company Powerline Special Use Permit AmendmentDecision Signed Date: 12/02/2021
ForestsNational Forests In Texas
DistrictsAngelina Ranger District
Legal Land DescriptionNot Applicable
Special use management