Install and operate a 16 inch natural gas pipeline in a right-of-way 1,930 feet long and 20 feet wide. The pipeline will service wells on private surface landlocked by National Forest and Sam Rayburn Reservoir.
Location
administrative Compartment 15 and 16 along FM 1277 and CR 3370
Project timeline
1
Scoping Start
08/16/2021
2
Decision
10/2021 (Estimated)
3
Implementation
10/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Midcoast Energy LLC Natural Gas Pipeline Special Use Permit | Decision Signed Date: 10/12/2021 |
| Forests | National Forests In Texas |
| Districts | Angelina Ranger District |
| Legal Land Description | Not Applicable |