Decision Memo Completed

Utility ROW Along CR 3420

National Forests and Grasslands in Texas San Augustine, Texas National Forests In Texas All Units

Installation of a natural gas and saltwater disposal pipeline, designation of a 50ft - wide utility corridor x 2,034 ft - length. During installation width would be 75ft with 25 ft restored after installation.

Location

CR 3420, Compartment 25, San Augustine County

Project timeline

1
Scoping Start
02/25/2025
2
Decision
05/2025 (Estimated)
3
Implementation
05/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Natural Gas
Utility ROW Along CR 3420Decision Signed Date: 05/05/2025
ForestsNational Forests In Texas
DistrictsAngelina Ranger District
Legal Land DescriptionNot Applicable
Minerals and geologySpecial use management