Decision Memo Completed

FY15 Allegheny Reservoir Fish Habitat Improvement Project

Allegheny National Forest McKean; Warren, Pennsylvania Allegheny National Forest All Units

Fish habitat improvement activities in Allegheny Reservoir.

Location

Bays throughout the Allegheny Reservoir.

Project timeline

1
Scoping Start
05/05/2015
2
Decision
07/2015 (Estimated)
3
Implementation
07/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements
FY15 Allegheny Reservoir Fish Habitat Improvement ProjectDecision Signed Date: 07/15/2015
ForestsAllegheny National Forest
DistrictsBradford Ranger District
Legal Land DescriptionNot Applicable
Wildlife, fish, rare plants