Special use authorization to replace and maintain natural gas pipelines within an existing right of way on 19 acres of national forest system lands.
Location
Limestone Township between Tidioute/Allegheny River and Queen
Project timeline
1
Scoping Start
11/03/2016
2
Comment Period
06/08/2017
3
Objection Period Start
12/13/2017
4
Decision
02/2018 (Estimated)
5
Implementation
03/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Queen Gas Pipeline Project Special Use | Decision Signed Date: 02/21/2018 |
| Forests | Allegheny National Forest |
| Districts | Bradford Ranger District |
| Legal Land Description | Not Applicable |