The proposed action is to construct, maintain, and use a 4-inch diameter plastic natural gas pipeline within forest road 261 and along an oil and gas access road for the purpose of transporting natural gas from existing gas wells.

Location

Lot 146, Warrant 2560, Hamilton Township and Lots 179 and 186, Warrant 2575, Wetmore Township, McKean County, Pennsylvania

Project timeline

1
Scoping Start
09/19/2019
2
Decision
11/2019 (Estimated)
3
Implementation
11/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Minerals Or Geology Plans Of Operations
KC Midstream Solutions Forest Road 261 Special Use PipelineDecision Signed Date: 11/15/2019