Project timeline

1
Scoping Start
03/24/2022
2
Comment Period
03/24/2022
3
Objection Period Start
08/25/2022
4
Decision
11/2022 (Estimated)
5
Implementation
05/2023 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements
Spongy Moth Suppression SupplementDecision Signed Date: 11/02/2022