The project involves the design and reconstruction of the boat launch on the Big Muddy River. This project will redesign and replace the existing boat ramp, which accumulates sediment from the river and is often not usable.
Location
Jonesboro/Murphysboro Ranger District at the end of Oakwood Bottoms Road (Old Johns Spur Road) on the Big Muddy River.
Project timeline
1
Scoping Start
02/17/2005
2
Decision
03/2005 (Estimated)
3
Implementation
08/2005 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Big Muddy Boat Launch | Decision Signed Date: 03/17/2005 |
| Forests | Shawnee National Forest |
| Districts | Mississippi Bluffs Ranger District |
| Legal Land Description | T10S R3W Sec 2 |