Decision Memo Completed

Lincoln Memorial Interpretation Site Improvements

Shawnee National Forest Union, Illinois Mississippi Bluffs Ranger District

Improve the existing memorial site to include one new short path, two new life-size statues, and foundation/wall/walkway work around the existing memorial

Location

Lincoln Memorial Interpretation Site - Jonesboro, IL

Project timeline

1
Scoping Start
04/05/2007
2
Decision
04/2008 (Estimated)
3
Implementation
09/2008 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Heritage Resource Management; Trail Management; Travel Management
Lincoln Memorial Interpretation Site ImprovementsDecision Signed Date: 04/03/2008
ForestsShawnee National Forest
DistrictsMississippi Bluffs Ranger District
Facility managementHeritage resource managementRecreation management