This amendment would allow for electricity to be provided to private property. The line would be buried along the south side of the existing road, trenching, about 6 inches wide for 600 feet.
Location
Jackson and Union Counties
Project timeline
1
Scoping Start
04/05/2013
2
Comment Period
06/22/2013
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Egyptain Electric Special-Use Permit Amendment | Decision Signed Date: 08/11/2013 Legal Notice Date: 08/17/2013 |
| Forests | Shawnee National Forest |
| Districts | Shawnee National Forest All Units |
| Legal Land Description | Section 6, Township 11 South, Range 1 West, NWNW corner and Section 31, Township 10 South, Range 1 West, SESE corner, 3rd P.M. |