Ameren Power Generating Company needs a new permit to reconstruct seven-miles of an existing permitted electric transmission line system, to include lines, poles, and supporting structures. The line runs from Grand Tower to Makanda.
Location
Their permitted right-of-way across Forest land is located between Grand Tower and Makanda.
Project timeline
1
Scoping Start
04/05/2013
2
Comment Period
11/13/2014
3
Objection Period Start
03/08/2015
4
Decision
05/2015 (Estimated)
5
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Ameren Powerline Reconstruction Project | Decision Signed Date: 05/20/2015 |
| Forests | Shawnee National Forest |
| Districts | Shawnee National Forest All Units |
| Legal Land Description | Township 10 South, Range 3 West Section 8, 13, 14, 15, 16, 17, 20, 21, & 27 |