The proposed actions encourage resilient forest conditions through silvicultural treatments including commercial thinning that will enhance the diversity of native vegetation on about 53 acres.
Location
The Ramsey Branch project area is about 1 mile east of Eddyville, IL.
Project timeline
1
Scoping Start
12/16/2013
2
Comment Period
10/31/2014
3
Objection Period Start
04/26/2015
4
Decision
09/2015 (Estimated)
5
Implementation
11/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Ramsey Branch Hardwood Restoration | Decision Signed Date: 09/23/2015 |
| Forests | Shawnee National Forest |
| Districts | Hidden Springs Ranger District |
| Legal Land Description | T12S, R6E, Sec 5 |