The decision would issue a new permit to allow for the construction, use and maintenance of a 600 foot by 20 foot or 0.11 mile, right-of-way (ROW) across Forest land for ingress and egress to private property.
Location
About 2 miles south of Equality
Project timeline
1
Scoping Start
10/15/2015
2
Decision
10/2015 (Estimated)
3
Implementation
11/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| C.M. Special-Use Permit Issuance | Decision Signed Date: 10/23/2015 |
| Forests | Shawnee National Forest |
| Districts | Hidden Springs Ranger District |
| Legal Land Description | NWSE Section 32, Township 9 South, Range 8 East, 3rd P.M |