The proposed Gale to Clear Creek Powerline Reconstruction project consists of 2.65 miles of 69,000 Volt Transmission line in existing right of way within the Shawnee National Forest.
Location
Gale to Clear Creek
Project timeline
1
Scoping Start
04/05/2017
2
Decision
12/2017 (Estimated)
3
Implementation
01/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Ameren: Gale to Clear Creek | Decision Signed Date: 12/14/2017 |
| Forests | Shawnee National Forest |
| Districts | Mississippi Bluffs Ranger District |
| Legal Land Description | NESW, Section 3, Township 15 South Range 3 West, E1/2W1/2, Section 34, Township 14 South Range 3 West |