Decision Memo Completed

Ameren: Gale to Clear Creek

Shawnee National Forest Alexander, Illinois Mississippi Bluffs Ranger District

The proposed Gale to Clear Creek Powerline Reconstruction project consists of 2.65 miles of 69,000 Volt Transmission line in existing right of way within the Shawnee National Forest.

Location

Gale to Clear Creek

Project timeline

1
Scoping Start
04/05/2017
2
Decision
12/2017 (Estimated)
3
Implementation
01/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Ameren: Gale to Clear CreekDecision Signed Date: 12/14/2017
ForestsShawnee National Forest
DistrictsMississippi Bluffs Ranger District
Legal Land DescriptionNESW, Section 3, Township 15 South Range 3 West, E1/2W1/2, Section 34, Township 14 South Range 3 West
Special use management