Decision Memo Completed

MM Waterline

Shawnee National Forest Union, Illinois Shawnee National Forest All Units

The proposal is to amend a special-use permit which would allow for the installation, maintenance, and operation of 1,320 feet long by 2 feet wide or 0.06 acre right-of-way across National Forest System land for an underground water transmission line

Location

This project is located in Union County, Illinois.

Project timeline

1
Scoping Start
04/13/2018
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
MM WaterlineDecision Signed Date: 08/22/2018
ForestsShawnee National Forest
DistrictsMississippi Bluffs Ranger District
Legal Land DescriptionNot Applicable
Special use management