Improve utility performance by removing old lines and putting in new lines closer to the road.
Location
Project one is located at the intersection of Highway. 93 and C-4. Project two is at the intersection of Highway. 93 and C-29.
Project timeline
1
Scoping Start
08/14/2014
2
Decision
01/2015 (Estimated)
3
Implementation
01/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission |
| AEP (Ohio Power) Amendments | Decision Signed Date: 01/09/2015 |
| Forests | Wayne National Forest |
| Districts | Ironton Ranger District |
| Legal Land Description | Sec. 21 T.2N. R.18W. and Sec. 29 T.2N. R.18W. |