Decision Memo Completed

Ohio Power Company Amendments

Wayne National Forest Gallia; Lawrence, Ohio Ironton Ranger District

Improve utility performance by removing old lines and putting in new lines closer to the road.

Location

Project one is located at the intersection of Highway. 93 and C-4. Project two is at the intersection of Highway. 93 and C-29.

Project timeline

1
Scoping Start
08/14/2014
2
Decision
01/2015 (Estimated)
3
Implementation
01/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission
AEP (Ohio Power) AmendmentsDecision Signed Date: 01/09/2015
ForestsWayne National Forest
DistrictsIronton Ranger District
Legal Land DescriptionSec. 21 T.2N. R.18W. and Sec. 29 T.2N. R.18W.