Environmental Assessment · Wenatchee River Ranger District · updated 6/9/2026
The Eagle Creek project area is 5,130 acres located on the Wenatchee River Ranger District, northeast of Leavenworth, Washington. · Chelan, Washington

Commercial, non-commercial, and fuels activities to reduce wildfire risk, improve timber sands and forest structure, and improve wildlife habitat.

Forest productsFuels managementWildlife, fish, rare plants
NEPA Start Date
2/18/2026
Finding/Decision Date
6/5/2026
Project documents
Erica Taecker · erica.taecker@usda.gov
NEPA / regulatory detail
Decision Signed Date6/5/2026
Midnight Restoration Developing Proposal
Environmental Assessment · Methow Valley Ranger District · updated 5/26/2026

Landscape-scale wildfire risk reduction and terrestrial restoration project in Rader Creek, lower Wolf Creek, and upper Twisp River drainages. Excludes Lake Chelan-Sawtooth Wilderness.

Forest productsFuels managementRoad managementVegetation management (other than forest products)Watershed managementWildlife, fish, rare plants
NEPA Start Date
Finding/Decision Date
Dan Leininger · daniel.leininger@usda.gov
Upper Methow Developing Proposal
Environmental Assessment · Methow Valley Ranger District · updated 5/26/2026

Landscape-scale wildfire risk reduction and terrestrial restoration project in Goat Creek, Cub Creek and Lost River drainages using emergency authorities.

Forest productsVegetation management (other than forest products)Watershed managementWildlife, fish, rare plants
NEPA Start Date
Finding/Decision Date
Project documents
Dan Leininger · daniel.leininger@usda.gov
Upper Swauk Restoration Project Developing Proposal
Environmental Assessment · Cle Elum Ranger District · updated 5/26/2026 · decision 10/2024 (Estimated)
36,567 acres. Thirteen miles northeast of Cle Elum, WA near Liberty, WA. See figure 1. T 20N, R 17E; T 20N, R 18E; T 21N R 17E; T 21N R 18E; T 22N, R 17E; Willamette Meridian. Kittitas and Chelan Counties, WA. · Chelan; Kittitas, Washington

Fuels & Forest Health EAD Project. Proposing forest restoration activities including commercial and non-commercial thinning, prescribed fire, fuels breaks, aquatic restoration activities, and transportation system changes.

Forest productsFuels managementRoad managementWatershed managementWildlife, fish, rare plants
NEPA Start Date
10/10/2023
Finding/Decision Date
Project documents
Scott Robinson · scott.robinson@usda.gov
Environmental Impact Statement · Okanogan-Wenatchee National Forest · updated 5/22/2026
Okanogan-Wenatchee National Forest · Chelan; Kittitas; Yakima, Washington

Proposal to amend Land and Resource Management Plans to provide forest plan direction for managing domestic sheep and goat grazing within the range of Bighorn sheep to better provide for bighorn sheep viability in the context of range management.

Grazing managementLand management planningWildlife, fish, rare plants
NEPA Start Date
Finding/Decision Date
Project documents
David Topolewski · david.topolewski@usda.gov
Environmental Assessment · Naches Ranger District · updated 5/21/2026
The SFT Project is located on the ancestral lands of the YN. This project is adjacent to the reservation boundary within the Naches Ranger District of the Okanogan–Wenatchee National Forest in Yakima County, Washington.

Wildfire Crisis Strategy Project

Fuels managementVegetation management (other than forest products)
NEPA Start Date
Finding/Decision Date
c/o Naches Ranger District
Decision Memo · Cle Elum Ranger District · updated 5/7/2026
North of I-90, approximately 7 miles northwest of the city of Cle Elum, along the east side of Cle Elum Lake and both side of Salmon la sac rd (SR903), along FSR 4303 and 4303-201. · Kittitas, Washington

Establish linear fuel breaks around lower Lake Cle Elum to reduce the risk of uncharacteristic wildfire, incorporating existing linear features.

Fuels management
Scoping Start
02/14/2024
Decision
05/2026 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
Scott Robinson · Scott.Robinson@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.3(11)
Special Authority2021 Infrastructure: Fuel Break Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsOkanogan-Wenatchee National Forest
DistrictsCle Elum Ranger District
Legal Land DescriptionPortions of T20N R14E, T21N R14E, and T22N R14E, W.M.
Environmental Assessment · Wenatchee River Ranger District · updated 1/29/2026
general area is Chumstick, Lower Peshastin, Leavenworth surrounding area · Chelan, Washington

Landscape scale terrestrial restoration project.

Fuels managementWatershed management
Scoping Start
09/25/2023
Comment Period
08/2025 (Estimated)
12/2025 (Estimated)
Decision
12/2025 (Estimated)
Implementation
01/2026 (Estimated)
Project documents
Erica Taecker · Erica.Taecker@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other; 2021 Infrastructure: Emergency Actions
Notice and Comment Regulation2021 Infrastructure: Emergency Actions
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Green)
ForestsOkanogan-Wenatchee National Forest
DistrictsWenatchee River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Cle Elum Ranger District · updated 6/30/2025
The project is located at the terminus of FS-4600, adjacent to the Upper Kachess River. · Kittitas, Washington

This project would decommission approx. 1 mile of FS-4600 (Mineral Creek Road), which would no longer be needed after the Upper Kachess River Restoration project constructs a new trailhead for the Mineral Creek Trail.

Wildlife, fish, rare plants
Scoping Start
07/2025 (Estimated)
Comment Period
07/2025 (Estimated)
Objection Period Start
08/2025 (Estimated)
Decision
09/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
Christopher Trinies · christopher.trinies@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Species Habitat Improvements
ForestsOkanogan-Wenatchee National Forest
DistrictsCle Elum Ranger District
Legal Land DescriptionT. 22N., R. 13 E., Sections 5 and 8
Decision Memo · Wenatchee River Ranger District · updated 5/22/2025
The project would occur along the Anderson Canyon to Coles Corner 115 kV transmission line. · Chelan, Washington

The project proposes aerial fiber optic installation, use, operation, and maintenance along roads within the existing transmission line right-of-way.

Special use management
Scoping Start
06/2025 (Estimated)
Decision
08/2025 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
Sarah Cudworth · Sarah.Cudworth@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsOkanogan-Wenatchee National Forest
DistrictsWenatchee River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Naches Ranger District · updated 3/5/2025
Approximately 55 miles west of Yakima, WA and 20 miles east of Packwood, WA. · Lewis; Yakima, Washington

White Pass proposes to replace the existing double chairlift with a new quad chairlift. The new lift would be installed in the same alignment as the current lift, with the same bottom and top terminal locations.

Special use management
Scoping Start
01/08/2025
Decision
03/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Kimberly Larned · kimberly.larned@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
ForestsOkanogan-Wenatchee National Forest
DistrictsNaches Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Methow Valley Ranger District · updated 2/25/2025
One bridge will cross Canyon Creek on the Jackita Ridge trail #738. The other bridge will cross Trout Creek on the W. Fork Methow trail #480. · Okanogan; Whatcom, Washington

Replace damaged trail bridges at Jackita Ridge trail # 738 over Canyon Creek and W. Fork Methow trail #480 over Trout Creek.

Recreation management
Scoping Start
07/02/2024
Decision
09/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
Rosemary Seifried · rosemary.seifried@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
ForestsOkanogan-Wenatchee National Forest
DistrictsMethow Valley Ranger District
Legal Land DescriptionT37N, R14E S12 and T36, R18 S4.
Environmental Assessment · Cle Elum Ranger District · updated 1/24/2025
Gold Creek drainage near Alpine Lakes Wilderness to Lake Keechelus · Kittitas, Washington

A multi-partner effort to recover Gold Creek bull trout populations by correcting habitat conditions which create significant mortality, reconnecting the creek and floodplain, and restoring natural processes. Provide recreation at this valued site.

Wildlife, fish, rare plants
Scoping Start
03/13/2020
Comment Period
04/03/2024
Objection Period Start
08/02/2024
Decision
12/2024 (Estimated)
Implementation
03/2025 (Estimated)
Project documents
Patricia GarveyDarda · patricia.garveydarda@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecies Habitat Improvements
ForestsOkanogan-Wenatchee National Forest
DistrictsCle Elum Ranger District
Legal Land DescriptionT 22N, R 11E, Sec 1, 2, 10, 11, 14, 15, 22, 23, 26, 27, 34, 35; T 21N, R 11E, Sec 1, 2, 11, 12, 13; T21N, R12E Sec 10
Environmental Assessment · R6 - Pacific Northwest Region All Units · updated 12/12/2023
The trail begins at the Continental Divide in Glacier National Park and travels 1,200 miles through 7 National Forests, 3 National Parks, BLM, state, tribal, municipal and private lands in MT, ID, WA. · Bonner; Boundary; Flathead; Glacier; Lincoln; Clallam; Ferry; Island; Jefferson; Okanogan; Pend Oreille; Skagit; Stevens; Whatcom, Idaho; Montana; Washington

The Comprehensive Plan will develop administrative and management objectives and practices and desired conditions for the Pacific Northwest National Scenic Trail on public lands in Forest Service Regions 1 and Regions 6.

Recreation managementSpecial area management
Scoping Start
11/01/2017
Comment Period
03/16/2023
Objection Period Start
07/13/2023
Decision
11/2023 (Estimated)
Implementation
01/2024 (Estimated)
Project documents
Lisa Romano · lisa.romano@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityPlan Creation/Revision; Trail Management; Special Area Management
Pacific Northwest National Scenic Trail Comprehensive Plan Decision NoticeDecision Signed Date: 11/13/2023
ForestsIdaho Panhandle National Forest; Flathead National Forest; Kootenai National Forest; Mt Baker-Snoqualmie National Forest; Olympic National Forest; Okanogan-Wenatchee National Forest; Colville National Forest
DistrictsBonners Ferry Ranger District; Priest Lake Ranger District; Glacier View Ranger District; Rexford Ranger District; Fortine Ranger District; Three Rivers Ranger District; Mt Baker Ranger District; Olympic National Forest All Units; Methow Valley Ranger District; Republic Ranger District; Sullivan Lake Ranger District; Tonasket Ranger District; Three Rivers Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Okanogan-Wenatchee National Forest All Units · updated 6/5/2023
approximately 10 developed seed orchards across the forest · Chelan; Douglas; Kittitas; Yakima, Washington

Maintain and protect developed tree seed orchards by thinning trees and maintaining fuel break in the surrounding 300 foot buffer.

Vegetation management (other than forest products)
Scoping Start
05/01/2023
Decision
01/1970 (Estimated)
Implementation
11/2023 (Estimated)
Project documents
Erin Baumgart · Erin.Baumgart@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Facility Maintenance
Decision Decided Date06/17/2026
ForestsOkanogan-Wenatchee National Forest
DistrictsOkanogan-Wenatchee National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Wenatchee River Ranger District · updated 6/5/2023
Icicle Creek Road from MP 4.3 to 4.8 · Chelan, Washington

Provide rockfall mitigation on up to three slopes on Icicle Creek Road from MP4.3 to 4.8. Project is scheduled to be completed Fall of 2023.

Road management
Scoping Start
12/05/2022
Decision
01/1970 (Estimated)
Implementation
08/2023 (Estimated)
Project documents
Kayli Barber · kayli.barber@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Decision Decided Date06/17/2026
ForestsOkanogan-Wenatchee National Forest
DistrictsWenatchee River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · R6 - Pacific Northwest Region All Units · updated 4/7/2023
National Forest units, typically high elevation, where blister-rust resistant white-bark pine trees have been identified or are in screening, and areas that are high priority for new selections. · Baker; Deschutes; Douglas; Grant; Jefferson; Klamath; Lake; Lane; Union; Wallowa; Chelan; Ferry; King; Kittitas; Okanogan; Pend Oreille; Skagit; Snohomish; Stevens; Whatcom; Yakima, Oregon; Washington

The Pacific Northwest Region is collaborating with nine Forests to develop a region-wide project to protect whitebark pine trees (Pinus albicaulis) that have a high level of white pine blister rust resistance.

Wildlife, fish, rare plantsVegetation management (other than forest products)
Scoping Start
04/2023 (Estimated)
Decision
09/2023 (Estimated)
Implementation
09/2023 (Estimated)
Project documents
Claire Ellwanger · claire.ellwanger@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
ForestsDeschutes National Forest; Fremont-Winema National Forest; Malheur National Forest; Mt Baker-Snoqualmie National Forest; Umatilla National Forest; Umpqua National Forest; Wallowa-Whitman National Forest; Okanogan-Wenatchee National Forest; Colville National Forest
DistrictsDeschutes National Forest All Units; Fremont-Winema National Forest All Units; Malheur National Forest All Units; Mt Baker-Snoqualmie National Forest All Units; Umatilla National Forest All Units; Umpqua National Forest All Units; Wallowa-Whitman National Forest All Units; Okanogan-Wenatchee National Forest All Units; Colville National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Cle Elum Ranger District · updated 12/9/2022
T. 22 N, R 15 E. Sec 10 NE 1/4 · Kittitas, Washington

Issue 2-year transitional priority use special use authorization for seasonal (winter) lodging facilities and outfitter guiding at DeRoux Campground, North Fork Teanaway River.

Special use management
Scoping Start
07/28/2022
Decision
12/2022 (Estimated)
Implementation
12/2022 (Estimated)
Project documents
Kimberly Larned · kimberly.larned@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (12), 36 Cfr 220.6(D)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Decided Date12/09/2022
ForestsOkanogan-Wenatchee National Forest
DistrictsCle Elum Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Chelan Ranger District · updated 10/13/2020
Lucerne fan south of Driftwood Harbor · Chelan, Washington

Temporarily place 6-10 ecology blocks above OHW to deflect overbank flows from Railroad Creek away from a potential avulsion low spot that flows directly into Driftwood Harbor.

Watershed management
Scoping Start
09/01/2018
Decision
10/2020 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
Matt Karrer · mkarrer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Decision Decided Date10/13/2020
ForestsOkanogan-Wenatchee National Forest
DistrictsChelan Ranger District
Legal Land DescriptionT31N R18E Sec10 NW 1/4
Decision Memo · Entiat Ranger District · updated 10/5/2020
Along Roads: 5700-000 (Tyee Ridge Road), 5703-000 (Windy Creek Rd), 5703-300 (Camp Nine Rd), 5709-00 (Windy Tie Rd) and 5711-000 (Upper Windy Road) · Chelan, Washington

The Forest Service is proposing the removal of dead trees within 150 feet of selected roads. Any tree that is dead, and is within 150 feet of the road, will be subject to removal regardless of species.

Road managementFuels management
Scoping Start
08/14/2019
Decision
10/2020 (Estimated)
Implementation
09/2019 (Estimated)
Project documents
Mariah Mayfield · mariahmayfield@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Decision Decided Date10/05/2020
ForestsOkanogan-Wenatchee National Forest
DistrictsEntiat Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Entiat Ranger District · updated 10/5/2020
T29N, R18E, Sec 27; Road No. 5100-000, 5606-000, 5608-000, 5900-000 · Chelan, Washington

Removal of dead trees within 150 feet of selected roads to address potential of dead trees falling on vehicles or people and blocking ingress/egress.

Road management
Scoping Start
01/09/2020
Decision
10/2020 (Estimated)
Implementation
05/2020 (Estimated)
Project documents
Jonathan Meier · jmeier02@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Decision Decided Date10/05/2020
ForestsOkanogan-Wenatchee National Forest
DistrictsEntiat Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Wenatchee River Ranger District · updated 10/5/2020
T26N, R16E, S1 · Chelan, Washington

Project is to issue a road use permit to T-Mobile to complete light maintenance road repairs to FSR6910 to the communications site on Round Mountain.

Road management
Scoping Start
07/10/2018
Decision
10/2020 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
Kevin Smith · kwsmith@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Decision Decided Date10/05/2020
ForestsOkanogan-Wenatchee National Forest
DistrictsWenatchee River Ranger District
Legal Land DescriptionNot Applicable