Environmental Assessment · Kisatchie National Forest All Units · updated 10/1/2025
60,000 Acres across the Kisatchie NF. · Grant; Natchitoches; Rapides; Vernon; Winn, Louisiana
Release Louisiana Pinesnakes on appropriate habitat of the Kisatchie NF
Wildlife, fish, rare plants
Comment Period
03/14/2025
Objection Period Start
04/25/2025
Decision
06/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Population Enhancements |
| Louisiana Pinesnake Reintroduction Project DN and FONSI | Decision Signed Date: 06/13/2025 |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District; Calcasieu Ranger District; Kisatchie Ranger District; Winn Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Calcasieu Ranger District · updated 9/25/2025
1,134 acres on the Evangeline Unit of the Calcasieu Ranger District, Kisatchie National Forest. · Rapides, Louisiana
Commercial harvest and restoration to reduce the risk of Insect and Disease.
Forest productsVegetation management (other than forest products)Fuels management
Decision
09/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Kisatchie National Forest |
| Districts | Calcasieu Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Kisatchie National Forest All Units · updated 12/17/2024
Kisatchie National Forest Lands in Natchitoches and Vernon Parishes that are currently used by Fort Johnson. · Natchitoches; Vernon, Louisiana
The Proposed Action will allow the JRTC and Fort Johnson to continue utilizing 98,125 acres of Kisatchie National Forest lands for military training activities critical to their readiness mission.
Special use management
Decision
12/2024 (Estimated)
Implementation
01/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (1982) |
| Project Activity | Special Use Authorizations |
| Forests | Kisatchie National Forest |
| Districts | Kisatchie National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Kisatchie National Forest All Units · updated 12/17/2024
Forest-wid · Claiborne; Grant; Natchitoches; Rapides; Vernon; Webster; Winn, Louisiana
The purpose of the project is to treat terrestrial and aquatic invasive plant species occurring forest-wide in the KNF. In addition to nonnative invasive species, the project would treat some native species that are problematic in certain areas.
Vegetation management (other than forest products)Special use management
Comment Period
04/21/2023
Objection Period Start
03/01/2024
Decision
12/2024 (Estimated)
Implementation
01/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Special Use Authorizations; Noxious Weed Treatments; Road Maintenance |
| Forests | Kisatchie National Forest |
| Districts | Kisatchie National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Catahoula Ranger District · updated 8/5/2024
Compartments 35, 36, 52, 53 & 54 · Grant, Louisiana
The project area is approximately 5,572 acres which includes activities of thinning, clearcutting, site preparing, planting of yellow pine, releasing seedlings, mechanical fuel reduction, herbicide application, RCW cavity installation, etc.
Vegetation management (other than forest products)
Comment Period
11/16/2023
Objection Period Start
02/28/2024
Decision
08/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Catahoula Ranger District · updated 3/31/2023
Along LA Hwy 8. · Grant, Louisiana
Place a fiber-optic cable along the southwest side of LA-8 beginning approximately 90 ft. west of LA-8 proceeding west along the southwest & northwest side of LA-8 for approximately 1.33 miles to #6461 Then south for .289 ft.
Special use management
Decision
05/2023 (Estimated)
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | T1W R6N Sec. 7 & 8 |
Decision Memo · Calcasieu Ranger District · updated 10/27/2022
Calcasieu Ranger Districts sites Kincaid, Little Cypress, and Enduro and all public used trails · Rapides; Vernon, Louisiana
Trail and Site repair on the Calcasieu Ranger District
Recreation management
Decision
10/2022 (Estimated)
Implementation
11/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Decision Decided Date | 10/27/2022 |
| Forests | Kisatchie National Forest |
| Districts | Calcasieu Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Catahoula Ranger District · updated 9/29/2022
Compartments 98-104 in the Old Camp Livingston Army Base area. · Grant; Rapides, Louisiana
Presently, the trail system is closed due to severe resource damage from hurricane and tornado events. This project will rehabilitate the trail to a sustainable grade and condition.
Recreation management
Decision
12/2022 (Estimated)
Implementation
05/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Winn Ranger District · updated 12/2/2020
Section 25, 35 & 36 T11N-R4W, and sections 3 & 9 of T10N-R4W In Winn Parish · Winn, Louisiana
Renew or re-issue a special use permit to City of Winnfield for maintenance and operation of a 6" waterline to the CCA or Prison Facility on the Gum Springs Rd.
Special use management
Decision
12/2020 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 12/02/2020 |
| Forests | Kisatchie National Forest |
| Districts | Winn Ranger District |
| Legal Land Description | Not Applicable |