Prescribed Fire Project Developing Proposal
Environmental Assessment · Shawnee National Forest · updated 5/27/2026 · decision 1/2027 (Estimated)
The entire Shawnee National Forest

The Shawnee National Forest (SNF or the Forest) proposes to restore and maintain fire-adapted ecosystems and reduce wildfire risk by applying prescribed fire at a landscape level throughout the entire Forest.

Fuels managementVegetation management (other than forest products)
NEPA Start Date
1/1/2026
Finding/Decision Date
Project documents
Jesse Riechman · jesse.riechman@usda.gov
Decision Memo · Shawnee National Forest All Units · updated 1/30/2026
Jackson County, Illinois (Raddle Quad) - Kinkaid T8S, R4W, Sections 17, 20, 28, and 29. · Jackson, Illinois

Electrical Transmission Powerline Improvement - Soil Boring, Access Road Improvements, Pole Replacement, and Right-of-Way Widening

Land management planningVegetation management (other than forest products)Special use managementFacility management
Scoping Start
01/13/2026
Decision
02/2026 (Estimated)
Implementation
02/2026 (Estimated)
Project documents
Kyle Varel · kyle.varel@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission
ForestsShawnee National Forest
DistrictsShawnee National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Shawnee National Forest All Units · updated 7/3/2025
FSR 494 Street Road (also known and referred to as Glen Street Road and Jackson Falls Road) from the intersection of the county road (Ozark Road) to the Jackson Falls parking area · Pope, Illinois

Upgrade 1.9 miles of FSR 494 Street Road (Glen Street Road, Glen Street Falls Road or Jackson Falls Road)also Jackson Falls trailhead parking area would be improved, expanded, and hardened with oil and chip pavement.

Road management
Scoping Start
07/03/2025
Decision
07/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
Cindy Morris · cynthia.morris1@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (24), 36 Cfr 220.6(E)(24)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Road Improvements/Construction
ForestsShawnee National Forest
DistrictsHidden Springs Ranger District
Legal Land DescriptionT 11 S, R 5 E, Sections 30 and 32 and T 12 S, R 5 E, Section 5
Max Creek Salvage In Progress
Decision Memo · Shawnee National Forest All Units · updated 7/2/2025
Johnson County, approximately 6 miles north of Vienna, Illinois on Taylor Ridge Road off Highway 45. · Johnson, Illinois

Timber salvage

Vegetation management (other than forest products)
Scoping Start
07/01/2025
Decision
08/2025 (Estimated)
Implementation
08/2025 (Estimated)
Project documents
Anastacia Hanauer · anastacia.hanauer@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Timber Sales (Salvage)
ForestsShawnee National Forest
DistrictsHidden Springs Ranger District
Legal Land DescriptionT12S., R3E., Sec 13 and T12S., R4E., Secs. 7, and 18
Environmental Assessment · Shawnee National Forest All Units · updated 6/17/2025
Located in Jackson County, Illinois. · Jackson, Illinois

Proposed project is a combined effort between the U.S. Army Corps of Engineers, as the lead agency, and the Forest Service, as the cooperating agency to restore the natural ecosystem functions of the Oakwood Bottoms Greentree reservoir system.

Wildlife, fish, rare plantsVegetation management (other than forest products)Watershed management
Scoping Start
10/22/2020
Comment Period
10/23/2020
Objection Period Start
03/29/2025
Decision
05/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
Leonard Pitcher · leonard.j.pitcher@usda.gov
NEPA / regulatory detail
Special AuthorityNepa Document Prepared By Another Federal Agency
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityForest Vegetation Improvements; Watershed Improvements
ForestsShawnee National Forest
DistrictsMississippi Bluffs Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Shawnee National Forest All Units · updated 6/17/2025
National forest lands near One Horse Gap in Pope County, Illinois. · Pope, Illinois

This proposal includes the removal of trees so that more sunlight will reach the forest floor, a step necessary to ensure that oak and hickory trees can successfully reproduce and grow.

Vegetation management (other than forest products)
Scoping Start
01/31/2025
Objection Period Start
03/29/2025
Decision
05/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
Leonard Pitcher · leonard.j.pitcher@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsShawnee National Forest
DistrictsHidden Springs Ranger District
Legal Land DescriptionTownship 11 South, Range 7 East, sections 28, 32, 33, & 3 and Township 12 South, Range 7 East, sections 3, 4, 5, 7, 8, 9, 16, and 17.