Approximately 1,980 acres are proposed for treatment that would include commercial harvest of trees. Mechanical treatment methods would be used to accomplish the treatment objective of Improve Stand Health and Vigor.
Location
Castle Mountains
Project timeline
1
Scoping Start
08/06/2024
2
Comment Period
08/06/2024
3
Objection Period Start
03/04/2025
4
Decision
06/2025 (Estimated)
5
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Bonanza | Decision Signed Date: 06/24/2025 |
| Forests | Lewis And Clark National Forest |
| Districts | White Sulphur Springs Ranger District |
| Legal Land Description | Not Applicable |