Integrated restoration project that includes vegetation, road, and recreation management activities to address multiple resource objectives. Project also includes forest plan amendment to change the management area allocation on approx. 198 acres.
Location
South of St. Regis between Interstate 90 and the Montana/Idaho border within the Dry, Cold, Little Joe, Twomile, and Ward Creek drainages
Project timeline
1
Scoping Start
08/06/2019
2
Comment Period
06/29/2020
3
Objection Period Start
02/01/2021
4
Decision
09/2024 (Estimated)
5
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Plan Amendment; Trail Management; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Redd Bull | Decision Signed Date: 09/27/2023 |
| Redd Bull DN 2 | Decision Signed Date: 09/27/2024 |
| Forests | Lolo National Forest |
| Districts | Superior Ranger District |
| Legal Land Description | T17 and 18N, R28 and 29W, P.M.M. |