The project proposes vegetation and road management activities to reduce hazardous fuels, restore fire resistant vegetative conditions, maintain or restore fish and wildlife habitat, and provide for public health and safety.
Location
Forest lands on the Seeley Lake Ranger District North around Highway 83.
Project timeline
1
Scoping Start
08/29/2023
2
Comment Period
04/10/2025
3
07/11/2025
4
Decision
07/2025 (Estimated)
5
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | 2021 Infrastructure: Emergency Actions |
| Notice and Comment Regulation | 2021 Infrastructure: Emergency Actions |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Travel Management; Timber Sales (Green) |
| North Seeley Wildland Urban Interface - Highway 83 Project | Decision Signed Date: 07/11/2025 |
| Forests | Lolo National Forest |
| Districts | Seeley Lake Ranger District |
| Legal Land Description | Not Applicable |