The project is proposing to modify the original decision pertaining to the waterflow intake and water source as documented in the Decision Notice signed in 2012. The proposed action would allow for increased waterflow through the existing pipeline.
Location
Southern Black Hills -
Project timeline
1
Scoping Start
09/01/2021
2
Comment Period
10/07/2021
3
Objection Period Start
12/17/2022
4
Decision
02/2023 (Estimated)
5
Implementation
02/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Southern Black Hills Water System Supplemental EA | Decision Signed Date: 02/10/2023 |
| Forests | Black Hills National Forest |
| Districts | Hell Canyon Ranger District |
| Legal Land Description | T6S, R4E, Sec 24; T6S, R5E, Sec 19, 20, 29 |