Authorize construction, operation and maintenance of a new approximately 1,295 foot water transmission main for the Grand Mesa Metropolitan District No. 2 water system to treat the water from two new off-forest wells.
Location
Section 30, T. 11S., R. 96 W., 6th Principal Meridian
Project timeline
1
Scoping Start
03/20/2025
2
Decision
05/2025 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Grand Mesa Metro District No. 2 Well Water Transmission Line | Decision Signed Date: 05/12/2025 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Valley Ranger District |
| Legal Land Description | Section 30, T. 11S., R. 96 W., 6th Principal Meridian |