Authorize the replacement of an existing concrete generator pad and propane generator at the New Cingular Wireless communication site lot.
Location
Uncompahgre Butte Com Site
Project timeline
1
Scoping Start
03/24/2025
2
Decision
04/2026 (Estimated)
3
Implementation
06/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Facility Maintenance |
| Decision Decided Date | 04/30/2026 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Valley Ranger District |
| Legal Land Description | Section 22, T. 50 N., R. 16 W., New Mexico Principal Meridian |