Decision Memo Completed

New Cingular Wireless Generator Pad and Generator Replacement Project (Uncompahgre Butte)

Grand Mesa, Uncompahgre and Gunnison National Forests Mesa, Colorado Grand Mesa Uncompahgre and Gunnison National Forest All Units

Authorize the replacement of an existing concrete generator pad and propane generator at the New Cingular Wireless communication site lot.

Location

Uncompahgre Butte Com Site

Project timeline

1
Scoping Start
03/24/2025
2
Decision
04/2026 (Estimated)
3
Implementation
06/2026 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Facility Maintenance
Decision Decided Date04/30/2026
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsGrand Valley Ranger District
Legal Land DescriptionSection 22, T. 50 N., R. 16 W., New Mexico Principal Meridian
Special use management